Contract delivery and cash decision worksheet Use one row per dated receipt or committed payment, then combine every live project on one thirteen-week calendar. The worked row is hypothetical. HYPOTHETICAL WORKED EXAMPLE — fixed values, not a recalculating model. Example 1 Job / movement: Refurbishment / first instalment Condition and evidence: Assessed £100,000 less assumed 5% retention; conditions to verify Expected bank date: End of week 4 Amount: £95,000 Decision consequence / owner: A two-week delay lifts the reserve gap to £105,000 before extra costs; commercial owner YOUR DECISION Critical payment condition Name the assessment, acceptance or release condition and its evidence. Your entry: __________________________________________________ Lowest cash week Include every live job and the reserve chosen for your business. Your entry: __________________________________________________ REVIEW TRIGGERS - Refresh when a variation, programme or expected receipt changes. - Pause additional non-refundable procurement if the agreed reserve would be breached before a credible remedy is secured.